July 27 (Reuters) - A U.S. appeals court on Friday vacated decisions by two federal agencies that allowed EQT Corp (NYSE:EQT) EQT.N to build its $3.5-billion to $3.7-billion Mountain Valley natural gas pipeline from West Virginia to Virginia across federal land.

The case is the latest victory in the U.S. Court of Appeals for the Fourth Circuit by the Sierra Club and other opponents of the pipeline.

Analysts at Height Capital Markets in Washington said the decision could delay the project's in-service date until the fourth quarter of 2019.

The Sierra Club and others challenged decisions by the U.S. Bureau of Land Management and the U.S. Forest Service granting the pipeline rights of way across federal land.

The court concluded certain aspects of the federal agencies' decisions failed to comply with the National Environmental Policy Act, the Mineral Leasing Act and the National Forest Management Act.

Officials at EQT were not immediately available for comment.

The court remanded the case back to the BLM and Forest Service for further proceedings.

Mountain Valley is one of several pipelines expected to enter service over the next year or two to connect growing output in the Marcellus and Utica shale basins in Pennsylvania, West Virginia and Ohio with customers in other parts of the United States and Canada. Thursday, EQT delayed the targeted completion date for Mountain Valley to the first quarter of 2019 from late 2018. explaining the delay, the company cited legal challenges in the Fourth Circuit by the Sierra Club and others to a permit issued by the U.S. Army Corps of Engineers that allowed the pipeline to cross streams and rivers in West Virginia, among other issues. 303-mile (488-kilometer) pipeline is designed to deliver up to 2 billion cubic feet per day of gas to meet growing demand for the fuel for power generation and other uses in the U.S. Southeast and Mid-Atlantic.

One billion cubic feet is enough gas to supply about five million U.S. homes for a day.

Mountain Valley is owned by units of EQT, NextEra Energy Inc (NYSE:NEE) NEE.N , Consolidated Edison Inc (NYSE:ED) ED.N , AlatGas Ltd ALA.TO and RGC Resources Inc RGCO.O . EQT Midstream Partners LP EQM.N will operate the pipeline and owns a significant interest in the venture.

In April, the companies said they planned to spend about $350 million to $500 million to extend the pipeline about 70 miles from Virginia into North Carolina by the fourth quarter of 2020. U.S. court sets Sept. hearing for EQT Mountain Valley natgas pipeline

FACTBOX-U.S. new natural gas pipeline projects

EQT Midstream to Expand Mountain Valley Pipeline to South

UPDATE 1-EQT delays W.V.-Va. Mountain Valley natgas pipe completion to Q1

Latest comments

Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.
© 2007-2024 - Fusion Media Limited. All Rights Reserved.