Sept 29 (Reuters) - Us Oil Sands Inc USO.V
* Us Oil Sands Inc. Announces pr spring project and liquidity update
* Planning to start up Pr Spring Project in Q4 this year as previously announced
* Pr Spring Project has also been completed and is ready for active mining operations
* Project total installed cost is now targeted to be under US$62.5 million, approximately 4% over original budget
* Completion, commissioning and start-up will need additional capital, co pursuing financing alternatives to meet liquidity requirements Source text for Eikon: ID:nCCN1YMGTX Further company coverage: USO (NYSE:USO).V