June 6 (Reuters) - Stornoway Diamond Corp SWY.TO :
* At end of may overall construction progress stood at 96
pct compared to recently re-baselined plan of 90 pct
* All major equipment and control systems have been
installed in diamond process plant, primary crusher, processed
Kimberlite load-out facility
* All critical path activities continue well within planned
schedule for first ore delivered to plant by end of September
* Stornoway provides Renard operational readiness update