Feb 3 (Reuters) - Stornoway Diamond Corp SWY.TO :
* Announces advanced renard construction schedule with reduced cost to complete
forecast
* Says first ore delivery to the renard diamond process plant has now been
scheduled for the end of September 2016
* Commercial production at the renard diamond process plan to be achieved by
December 31, 2016
* Estimated capital cost to complete for the project has been adjusted
downwards from C$811.0 million to C$775.4 million
* Source text for Eikon ID:nGNXMMFAQa